Meghalaya mishap Day 23: Submersible pumps to start ops tomorrow

Odhisa Fire Services personnel pump out water from old shaft; water level recedes by 3.5 ft; around 9, 00,000 litres of water pumped out so far

Sabra Nagi

Sabra Nagi

Shillong: Odisha Fire Services personnel resumed their operations to pump out water from the old shaft at 10.30 am on Friday of the ill-fated coal mine in Meghalaya's East Jaintia Hills district. A platform was also installed in the same shaft by the Coal India Limited team present at the site. This is the second shaft adjoining the main one where the team is undertaking its dewatering efforts from.

Odhisa Fire Services personnel were engaged all day long in pumping out water from the old shaft, and the water level receded by 3.5 ft. with the help of two pumps
Odhisa Fire Services personnel were engaged all day long in pumping out water from the old shaft, and the water level receded by 3.5 ft. with the help of two pumps
EastMojo image

The Kirloskar Brothers team, too, which was readying to lay a platform on the main shaft of the coal mine since Wednesday, was successful in laying down two pumps by Friday evening.

Operation spokesperson R Susngi told EastMojo that the Odisha Fire Services personnel were engaged all day long in pumping out water from the old shaft, and the water level receded by 3.5 ft with the help of two pumps, and around 9, 00,000 litres of water were pumped out in total.

Coal India Ltd was successful in installing the submersible pump into the old shaft around 3:30 pm on Friday afternoon
Coal India Ltd was successful in installing the submersible pump into the old shaft around 3:30 pm on Friday afternoon
EastMojo image

Meanwhile Coal India Ltd was successful in installing the submersible pump into the old shaft around 3:30 pm on Friday afternoon.

Around 9, 00,000 litres of water was pumped out in total
Around 9, 00,000 litres of water was pumped out in total
EastMojo image

Preparations are on to make all the pumps in both the old shafts and the main shaft operational by Saturday morning.